Project specifics: 

Project: King Edward's Parade

Location: Eastbourne, East Sussex

Contract: Design & Build

Value: £3,900,000

Case Study: Download

DESCRIPTION OF WORKS: 

A development of ten apartments and fourtown houseS for sale in the prestigious Meads area of Eastbourne.

Ellis was appointed formally by the client to manage the pre-construction phase. In this case the consultants were all direct employed by the client.

Following design development, risk management, value engineering and the development of the contract sum over a period of 11 weeks commencing in the spring of 2015 Ellis entered into formal contract in July.

A site start on the demolition of the existing building was made in September 2015 and the project is due for completion in early 2017.